Nuclear-1 Appeal Supplementary Submission

After a long process described described here Eskom was granted permission by the minister for the environment to build a new 4000 MW nuclear plant at Koeberg. After three years of silence, the process was revived as described here. We appealed for an extension,  and finally completed the submission below. Continue reading

Nuclear-1 EIA submission period re-opened

Letter from DEFF EIA supplemental submission extension grantedAfter three years of silence, the Nuclear-1 Environmental Impact Assessment process was revived by an invitation for “supplemental submissions”, as described in  Nuclear-1 EIA revived with ‘Supplemental Submissions’. The invitation specified a condition that supplemental submissions may only be made by those who had submitted a formal appeal in 2017. We wrote to the department and objected to this condition as follows:

Continue reading