NERSA conditional nuclear concurrence distracts from Koeberg problems

NERSA conditional concurrence with new nuclear

The National Energy Regulator of South Africa (NERSA) has given a conditional concurrence with the section 34 ministerial determination to proceed with procuring a new nuclear plant. This concurrence has some crucial suspensive conditions, in particular 1.3. This makes it clear that given the information put before NERSA, the decision to go ahead with a nuclear build cannot be considered rational.

Continue reading

Civil society responds to reports of Koeberg contract

It was recently widely reported in the media that a US-based engineering company has been awarded a portion of a R20bn contract to extend the life of the Koeberg nuclear power plant. Activists and civil organisations are concerned that the legal processes required to grant a licence for a life extension have not been followed.

Koeberg’s nuclear licence expires in 2024

In order to operate beyond 2024, Eskom needs the approval of the NNR, and a new licence to be issued. This licencing process is described in new regulations published in March 2021, which requires a notice in the government gazette as well as announcements in local newspapers. This would allow the public to make comments for the NNR to take into account before making a decision. However, it appears that this process has not been followed.

Continue reading

Ministerial agreement contradicts IRP 2019

Too much power

The responsibility of regulating the safety of nuclear installations in South Africa is concentrated in the hands of one man, who appoints not only the members of the National Energy Regulator of South Africa (NERSA), but also the CEO of the National Nuclear Regulator (NNR) , and its board via an opaque process. The same man has committed in writing to both procuring a new nuclear plant by 2024, and extending the life of Koeberg by 20 years beyond its design lifetime.

Ministerial performance agreements address poor service delivery
In 2019, in an attempt to address poor service delivery, President Ramaphosa required each national minister to sign a performance agreement. This was laudable, but in some cases has had unforeseen and negative consequences.

Continue reading

Eskom lawyers insist IRP 2019 must be ignored

After 17h00 on Thursday the 1st of April, the eve of the Easter weekend, Eskom’s response to the Nuclear-1 Environmental Authorisation (EA) appeal was released. This response marks the last step before Environment Minister Barbara Creecy makes a final decision on granting Eskom permission to build a new nuclear plant at the Koeberg site, 27kms north of the city of Cape Town.

According to civil organisations, the response document contains misinformation and worryingly shows Eskom pushing for a new nuclear build, overriding the country’s energy plan, the Integrated Resource Plan of 2019 (IRP 2019).

Continue reading

Eskom responds to Koeberg cracks

In response to our press release Cracks in Koeberg Safety Claims Eskom released a statement (full text given below) on 12 February 2021. This statement ignores several of the issues we raised, obfuscates others, and provides some further alarming information.

Maintenance and testing is being done …
The Eskom statement says “repairs have been implemented” which sounds initially reassuring. However, the report itself describes the repairs in progress at the time as follows:Extract from report: neither ideal nor sustainable

Continue reading

Nuclear-1 Appeal Supplementary Submission

After a long process described described here Eskom was granted permission by the minister for the environment to build a new 4000 MW nuclear plant at Koeberg. After three years of silence, the process was revived as described here. We appealed for an extension,  and finally completed the submission below. Continue reading

Koeberg Emergency Plan conflicts with COVID-19 regulations

Koeberg Population Density Map

Nuclear-1 EIA App E18

A nuclear incident requiring an evacuation around Koeberg would have a significant effect on the spread of COVID-19. During an evacuation, social distancing will not be followed as people pack into any available transport. Travel restrictions will either be suspended by the government, or overridden by the public possibly with bloodshed. No roadblock can stop 80 000 panicking people! Continue reading

Response from Eskom to our appeal against the Environmental Authorisation for Koeberg Nuclear site

Title page of response from Eskom to the KAA appeal

Back in 2007, Eskom began an Environmentam fcl Impact Assessment (EIA) for building a large new nuclear power plant on the Koeberg site, about 28km north of Cape Town. Ten years later, after many drafts and submissions, the Department of Environmental Affairs issued an Environmental Authorisation for the project to go ahead. Many organisations appealed this decision, and Eskom was required to respond in detail to the content of each of those appeals, which they have now done (in August 2018).

Many of these responses were combined into one document, which has been widely distributed. However, KAA received the following 115 page specific response. There has not been time to go through it in detail yet, but it is published below to give you all the opportunity to have a look through it and pass it on to others.

Paging through it, a few bits stood out for me.

A tourism plus…
In a show of optimism regarding possible impacts of tourism, Eskom writes “Some nuclear power stations have a positive effect on tourism, as tourists visit specifically to see the stations.”

Continue reading

Appeal against Environmental Authorisation for Koeberg

After a long Environmental Impact Assessment which began in 2007, an Environmental Authorisation was issued for the Koeberg site, 26km north of Cape Town.  This gave Eskom permission to build a new nuclear plant of unspecified design, plus a nuclear waste reprocessing and/or disposal site.

At first only 30 days were allowed for appeals against this decision, and this was extended on the day of the deadline to about 90 days, until 5th March 2017. There are so many reasons this Authorisation was wrong, and we tried to describe some of them in the 43 page submission we wrote. Continue reading

Extension Granted for Appeal Against Nuclear-1 Authorisation

On 11 October 2017 the Department of Environmental Affairs (DEA) issued an authorisation to Eskom for a second nuclear power plant at Koeberg, 28km north of Cape Town City centre.  This was in response to a final Environmental Impact Report submitted to the Department by Gibb (Pty) Ltd on behalf of Eskom, the applicant.

Please sir, may we have some more time?
We wrote to the Department on 30 October, requesting an extension of the 30 day appeal period, which was set to expire on 1 December 2017. Continue reading