Response from Eskom to our appeal against the Environmental Authorisation for Koeberg Nuclear site

Title page of response from Eskom to the KAA appealBack in 2007, Eskom began an Environmental Impact Assessment (EIA) for building a large new nuclear power plant on the Koeberg site, about 28km north of Cape Town.  Ten years later, after many drafts and submissions, the Department of Environmental Affairs issued an Environmental Authorisation for the project to go ahead.  Many organisations appealed this decision, and Eskom was required to respond in detail to the content of each of those appeals, which they have now done (in August 2018).

Many of these responses were combined into one document, which has been widely distributed.  However, KAA received the following 115 page specific response.  There has not been time to go through it in detail yet, but it is published below to give you all the opportunity to have a look through it and pass it on to others.

Paging through it, a few bits stood out for me.

A tourism plus…
In a show of optimism regarding possible impacts of tourism, Eskom writes “Some nuclear power stations have a positive effect on tourism, as tourists visit specifically to see the stations.”  Continue reading

Advertisements

Appeal against Environmental Authorisation for Koeberg

After a long Environmental Impact Assessment which began in 2007, an Environmental Authorisation was issued for the Koeberg site, 26km north of Cape Town.  This gave Eskom permission to build a new nuclear plant of unspecified design, plus a nuclear waste reprocessing and/or disposal site.

At first only 30 days were allowed for appeals against this decision, and this was extended on the day of the deadline to about 90 days, until 5th March 2017. There are so many reasons this Authorisation was wrong, and we tried to describe some of them in the 43 page submission we wrote. Continue reading

Extension Granted for Appeal Against Nuclear-1 Authorisation

On 11 October 2017 the Department of Environmental Affairs (DEA) issued an authorisation to Eskom for a second nuclear power plant at Koeberg, 28km north of Cape Town City centre.  This was in response to a final Environmental Impact Report submitted to the Department by Gibb (Pty) Ltd on behalf of Eskom, the applicant.

Please sir, may we have some more time?
We wrote to the Department on 30 October, requesting an extension of the 30 day appeal period, which was set to expire on 1 December 2017. Continue reading

Koeberg authorised to be Cape Town’s permanent radioactive waste dump

On 11 October 2017 the Department of Environmental Affairs (DEA) issued an authorisation to Eskom for a second nuclear power plant at Koeberg, 28km north of Cape Town City centre.  It came with a surprise.  The Department also authorised the “construction of facilities or infrastructure, including associated structures or infrastructure for … disposal of nuclear fuels, radioactive products and waste.

Waste disposal not part of project…
You would have been surprised if you had studied the final Environmental Impact Report (EIR) because it gave the impression this was not about waste disposal. Continue reading

Nuclear-1 Submission to Dept of Environmental Affairs

Before approval for a nuclear plant can be granted, by law an Environmental Impact Assessment (EIA) has to be done and submitted to the Department of Environmental Affairs (DEA).

The EIA for the so called ‘Nuclear-1’ project has been in progress for over six years, and the fourth and final draft of the resulting report was eventually submitted to the DEA in early 2016.

This report is of a low scientific standard, and should be rejected by the DEA.

We have made submissions on each draft to the EIA consultants, GIBB, which have been largely ignored, and have not resulted in the changes to the EIA report we hoped for.

We have therefore written to the DEA giving reasons why we believe they should reject this report.

To see our submission, including a short summary, click here: KAA Submission to DEA

Eskom and GIBB living in la-la land

Eskom and the Department of Energy have recently cranked up efforts to move forward with the plans for more nuclear energy for South Africa.  In the Environmental Impact Assessment being prepared by GIBB consultants, the background to this includes a graph of the predicted peak electricity demand. Here is the graph they use, on page 2 of the latest combined main report, released in September 2015: Continue reading

The Nuclear-1 video they didn’t want you to see

As for any large project, the proposed building of a new nuclear power plant in South Africa required an Environmental Impact Assessment (EIA) process to be completed by independent experts.  This results in an Environmental Impact Report (EIR) which must be presented to the public via a public participation process.

During some of these presentations, Peter Becker, of the Koeberg Alert Alliance videoed the proceedings. Continue reading