Response from Eskom to our appeal against the Environmental Authorisation for Koeberg Nuclear site

Title page of response from Eskom to the KAA appealBack in 2007, Eskom began an Environmental Impact Assessment (EIA) for building a large new nuclear power plant on the Koeberg site, about 28km north of Cape Town.  Ten years later, after many drafts and submissions, the Department of Environmental Affairs issued an Environmental Authorisation for the project to go ahead.  Many organisations appealed this decision, and Eskom was required to respond in detail to the content of each of those appeals, which they have now done (in August 2018).

Many of these responses were combined into one document, which has been widely distributed.  However, KAA received the following 115 page specific response.  There has not been time to go through it in detail yet, but it is published below to give you all the opportunity to have a look through it and pass it on to others.

Paging through it, a few bits stood out for me.

A tourism plus…
In a show of optimism regarding possible impacts of tourism, Eskom writes “Some nuclear power stations have a positive effect on tourism, as tourists visit specifically to see the stations.”  Continue reading

Advertisements

Appeal against Environmental Authorisation for Koeberg

After a long Environmental Impact Assessment which began in 2007, an Environmental Authorisation was issued for the Koeberg site, 26km north of Cape Town.  This gave Eskom permission to build a new nuclear plant of unspecified design, plus a nuclear waste reprocessing and/or disposal site.

At first only 30 days were allowed for appeals against this decision, and this was extended on the day of the deadline to about 90 days, until 5th March 2017. There are so many reasons this Authorisation was wrong, and we tried to describe some of them in the 43 page submission we wrote. Continue reading

Extension Granted for Appeal Against Nuclear-1 Authorisation

On 11 October 2017 the Department of Environmental Affairs (DEA) issued an authorisation to Eskom for a second nuclear power plant at Koeberg, 28km north of Cape Town City centre.  This was in response to a final Environmental Impact Report submitted to the Department by Gibb (Pty) Ltd on behalf of Eskom, the applicant.

Please sir, may we have some more time?
We wrote to the Department on 30 October, requesting an extension of the 30 day appeal period, which was set to expire on 1 December 2017. Continue reading

Koeberg authorised to be Cape Town’s permanent radioactive waste dump

On 11 October 2017 the Department of Environmental Affairs (DEA) issued an authorisation to Eskom for a second nuclear power plant at Koeberg, 28km north of Cape Town City centre.  It came with a surprise.  The Department also authorised the “construction of facilities or infrastructure, including associated structures or infrastructure for … disposal of nuclear fuels, radioactive products and waste.

Waste disposal not part of project…
You would have been surprised if you had studied the final Environmental Impact Report (EIR) because it gave the impression this was not about waste disposal. Continue reading

High Court blasts nuclear plans

Jubilant activists celebrate on the steps of the High Court

A case against the Department of Energy, the Minister of Energy and Eskom was brought by SAFCEI and EarthLife Africa Johannesburg recently.  Today judgement was handed down by Judge Bozalek, and it surprised everyone.  He granted every single request of the plaintiffs!  He also gave a costs order against the government. Continue reading

Would you like to earn R1.7m a week?

Drawing of Zizamele Mbambo

Zizamele Mbambo

On November 29 2016 the Portfolio Committee on Energy was given a presentation by the Department of Energy (DOE) on the progress of the South African nuclear build programme.  For some reason, the minister of energy, the Director General of the department and the Director General for nuclear energy chose not to attend, and instead sent the  Deputy Director General for nuclear energy, Mr Zizamele Mbambo.

The presentation included a list of sixteen consultancy contracts that have been awarded by the DOE. First prize for the most lucrative contract is a tie between Mahlako-A-Phahla Investments and Central Lake Trading 149, at about R1.7 million per week! Continue reading

Kelvin Kemm: Yet another pro-nuke advocate discredited

Drawing of Kelvin kemmIn South Africa there are few, if any, more vocal proponents of nuclear power than Kelvin Kemm, recently appointed chair of the Nuclear Energy Corporation of South Africa (NECSA) board.

Kemm was a proponent of the Pebble Bed reactor project (PBMR), which turned into an expensive failure for South African tax payers, who funded the project for somewhere around R10 billion.  Most of that went to salaries and consulting fees for those in the industry such as Kemm.

A local investigative magazine, Noseweek, did a bit of digging into Kemm, and came up with a lot of information about CFACT, or the Committee For A Constructive Tomorrow, which is a sugar coated name for a lobby group funded by oil and coal companies.

Hired to head CFACT was Marc Morano, an expert at disinformation. Continue reading