Eskom releases Koeberg Decommissioning Strategy

Koeberg is the only nuclear power plant in Africa, and is operated by Eskom under a licence issued by the National Nuclear Regulator. Section 17.2 of this licence specifies that “The licensee must submit for approval a decommissioning plan, as early as possible in the life cycle of the activity or facility. The plan should be revisited and updated as necessary.”

Using the Promotion of Access to Information Act in August 2020 we submitted a request to Eskom for a copy of this plan. In October 2020 they responded with a letter and the document below. Continue reading

Nuclear-1 EIA submission period re-opened

Letter from DEFF EIA supplemental submission extension grantedAfter three years of silence, the Nuclear-1 Environmental Impact Assessment process was revived by an invitation for “supplemental submissions”, as described in  Nuclear-1 EIA revived with ‘Supplemental Submissions’. The invitation specified a condition that supplemental submissions may only be made by those who had submitted a formal appeal in 2017. We wrote to the department and objected to this condition as follows:

Continue reading

A National Nuclear Decommissioning Policy?

On 20 July 2020, the Department of Mineral Resources and Energy (DMRE) released a Discussion Paper on National Decommissioning Policy for Nuclear Facilities.

This was a well balanced document which went into some detail, and proposed various decommissioning strategies. It posed 10 questions which covered liability and security for decommissioning costs, strategies, and research needed.

The actual costs of decommissioning the Koeberg Nuclear Power Station, including final disposal of the spent fuel (so far over 1.5 million kilograms),  are unknown. If South Africa had followed the Swedish model with a levy on nuclear power Eskom should have accumulated a fund of about R170bn by now. Instead, Eskom is R450bn in debt. Continue reading

Nuclear-1 EIA revived with ‘Supplemental Submission’ period

The Nuclear-1 Environmental Impact Assessment (EIA) for a large new nuclear plant at the Koeberg site was given the go ahead in 2017, resulting in many appeals against this decision.  After three years of silence, the Department sent out a notice to appellants in July 2020, inviting a supplemental submission.

The EIA was based heavily on the Integrated Resource Plan (IRP) 2010, which included projections of strong economic growth and vastly increased electricity demand by 2020, and hence the need for nuclear power stations. Recently the IRP 2019 was released, which took into account the actual electricity demand, and so delayed any possible need for new nuclear power to beyond 2030.

Despite the length of time that has passed with the EIA process in limbo, the Department have told us that interested parties may not make submissions now, unless they also submitted a formal appeal in 2017. The deadline for submissions is 3 September 2020, although this may be extended. Continue reading