IAEA report reveals 14 safety issues with Koeberg

In March 2022 a team from the International Atomic Energy Agency (IAEA) visited Koeberg to report on how ready the plant was to implement Eskom’s plan to extend its life beyond 2024. Eskom wanted to keep this report secret, but due to a request under the Promotion of Access to Information Act, it is now public.

The report lists fourteen safety issues with the planned life extension, or LTO (Long Term Operation), which mostly highlight that given the current conditions at Koeberg, the refurbishment cannot be done on time, nor safely. The full report is included below.

Continue reading

NNR Court case: The answering affidavit from Minister Mantashe

Minister Mantashe has submitted an affidavit to the High Court in response to a high court application by Peter Becker to review the decision by the Minister to dismiss him from the Board of the National Nuclear Regulator (NNR). Previous posts included the Founding Affidavit, the Supplementary Founding Affidavit and the Answering Affidavit from the NNR and NNR Board Chair. This is the only opportunity for the Minister to present evidence to the court.

The affidavit expresses the view that the function of NNR Board members is to ““Loyally execute the policies of the government of the day” which includes the life extension of Koeberg. The Minister characterises resistance to this plan as “political opposition”, misconduct, and a justified basis for dismissal.

Below is the text of the Answering Affidavit from Minister Mantashe, which is now in the public court record.

Continue reading

NNR Court case: The answering affidavit from the NNR and the Board Chair

In April 2021 Peter Becker launched a high court application to review the decision by Minister Mantashe to dismiss him from the Board of the National Nuclear Regulator (NNR). Previous posts included the Founding Affidavit and the Supplementary Founding Affidavit. After requesting and being granted a three week extension to the deadline, the Chair of the NNR Board, as the second respondent, and the NNR itself as the third, supplied their combined answering affidavit on 1 August 2022. This is the only opportunity for them to present evidence to the court.

Below is the text of the combined Answering Affidavit from the NNR Board Chair, which is now in the public court record:

Continue reading