Civil society rejects NNR public consultation process for Koeberg life extension

Koeberg comes to the end of its life in the second half of 2024 when Eskom’s licence issued by the National Nuclear Regulator (NNR) expires. Eskom has applied to the NNR for a twenty year extension to this licence and were required to prepare a Safety Case which described why such an extension would be safe. Initially, at a Public Safety Information Forum meeting on 31 March 2022, Eskom refused to release the Safety Case publicly but later backtracked and released a redacted version of it with many sections blacked out in January 2023. 

As part of the licence application, the NNR started a public consultation process on 8 January 2023 with a deadline for submissions on 16 March 2023. Due to the lack of transparency from Eskom, civil society organisations have rejected this process and demanded the complete suspension of the comment period.

Continue reading

IAEA report reveals 14 safety issues with Koeberg

In March 2022 a team from the International Atomic Energy Agency (IAEA) visited Koeberg to report on how ready the plant was to implement Eskom’s plan to extend its life beyond 2024. Eskom wanted to keep this report secret, but due to a request under the Promotion of Access to Information Act, it is now public.

The report lists fourteen safety issues with the planned life extension, or LTO (Long Term Operation), which mostly highlight that given the current conditions at Koeberg, the refurbishment cannot be done on time, nor safely. The full report is included below.

Continue reading

Koeberg costs South Africa

The Koeberg nuclear plant is the only nuclear power plant in Africa. Construction began in the 1970s and the plant came online in 1984. It operates under a licence from the National Nuclear Regulator (NNR) which expires in July 2024. In 2010 the Eskom Board approved spending R20bn on refurbishing Koeberg to extend its life by 20 years, provided that it received approval from the NNR. That approval has not as yet been given to Eskom by the NNR.

Currently Koeberg provides 3.5% of national nominal generating capacity, although over the past few years it has been plagued by problems. For most of 2022, unit 2 has been offline and the plant has run at half of its nominal capacity.

Continue reading

IAEA visit to Koeberg results in misunderstandings

The International Atomic Energy Agency (IAEA) visited the Koeberg Nuclear Power Plant near Cape Town from 22 to 31 March 2022. Both the IAEA and Eskom put out media statements after the visit, which are available on the Eskom and IAEA sites respectively. The statements have resulted in some misunderstanding, which we try to correct below.

Firstly, it is important to bear in mind that the IAEA is an organisation with voluntary membership and has the objective “to accelerate and enlarge the contribution of atomic energy”, according to its statute. Member states may invite the IAEA to visit a nuclear site to conduct a review and make recommendations, and this visit was done after a request from the Department of Mineral Resources and Energy.

Continue reading

NNR CEO resigns after approvals for Koeberg and as legal battles loom

On 18 March 2022, the National Nuclear Regulator (NNR) announced that Dr. Mzubanzi Bismark Tyobeka had resigned as the Chief Executive Officer of the organisation. This resignation comes at a busy time for the NNR as it considers Eskom’s application to extend the life of Koeberg Nuclear Power Plant and the Department of Mineral Resources and Energy talks about procurement of 2500MW new nuclear by 2024. 

Considering the implications, this resignation has raised questions from civil society.

Continue reading

Suspension of NNR Board member challenge: settlement reached

Issued by Rodney Anderson, of Save Bantamsklip

Save Bantamsklip | Xplorio Gansbaai

Six months after appointing a Board member to the Board of National Nuclear Regulator (NNR) in order to represent affected communities, Minister Mantashe unlawfully suspended Peter Becker on 18 January 2022. He has been a vocal campaigner against nuclear power in South Africa for about 12 years, and when Mantashe appointed him in June 2021 it was widely welcomed as an enlightened step. According to the NNR Act of 1999, the NNR Board also includes a member from the Department of Mineral Resources and Energy (DMRE), well known for a very pro-nuclear stance.

Continue reading

Modelling report: Koeberg life extension costs the country

It is generally agreed that nuclear power comes with an inherent risk. What is hotly debated is whether or not there are benefits which outweigh that risk. When it comes to the Koeberg Nuclear Power Plant, Eskom have had the approach that since Koeberg produces electricity at a cost of around R0.45 per kWh, it is a ‘no-brainer’ to spend whatever is needed on a refurbishment to extend the life of the plant beyond the end of its design life in 2024.

A recently released modelling report estimates that doing that refurbishment would result in additional costs of R50bn “from a combination of the actual costs of life extension, additional open cycle gas turbine (OCGT) usage, large key-customer curtailment requests/instructions, and scheduled load-shedding.” It will also increase carbon emissions due to the additional use of OCGTs.

Continue reading

Suspension of NNR Board member: Response

Further to our previous post re being excluded from Board meetings, and later receiving a letter from Minister Mantashe suspending him, Peter Becker’s legal representative wrote as below to the Minister.

It has since emerged that on the same day of the letter, 18 January 2022, Eskom received approval from the National Nuclear Regulator (NNR) to go ahead with the replacement of the first three steam generators at Koeberg.

It is a peculiar coincidence that based on a legal opinion delivered in early October 2021, the Minister happened to write the suspension letter on the day the NNR approved this major project, which is a key component of Eskom’s plan to extend the life of the ageing plant by twenty years.

Continue reading

Minister suspends Civil Society representative to NNR

Further to our previous post re being excluded from Board meetings, Peter Becker, the representative of communities potentially affected by decisions of the National Nuclear Regulator, has been formally suspended with immediate effect.

Becker strenuously denies all the allegations of ‘misconduct’ and ‘conflict of interest’ which have been made against him and hopes to challenge this decision and have it reversed.

Meanwhile, the Regulator presses forward with deliberating on what approvals to grant the Koeberg Nuclear plant at a critical time when work is about to start to extend its lifetime by twenty years. This is precisely the time when it would be in the public interest to have someone with Becker’s expertise involved in oversight of NNR processes.

Continue reading

Civil society representative excluded from NNR board

The National Nuclear Regulator (NNR) is tasked with protecting the public and the environment from radiation. The NNR Act of 1999 requires that the Board of the NNR includes a person representing civil society. Despite that, in 2020 civil society became progressively unhappy that there seemed to be no such representative.

After being nominated by several organisations in late 2020, in June 2021, Peter Becker of the Koeberg Alert Alliance was appointed to the Board to fulfil this role.

Currently, there is a lot of attention on the work being done at Koeberg which requires prior approval from the NNR. There are meetings of the Board this week where technical aspects of these matters will be discussed and decided on.

On Monday 17 January Becker was refused access to the agenda and document packs for these meetings by the Board secretary, and his access to the online document portal has been revoked. He wrote to the Board chair asking for a reason, but to date no response has been received. He also was not invited to the online meetings.

Continue reading