Civil society rejects NNR public consultation process for Koeberg life extension

Koeberg comes to the end of its life in the second half of 2024 when Eskom’s licence issued by the National Nuclear Regulator (NNR) expires. Eskom has applied to the NNR for a twenty year extension to this licence and were required to prepare a Safety Case which described why such an extension would be safe. Initially, at a Public Safety Information Forum meeting on 31 March 2022, Eskom refused to release the Safety Case publicly but later backtracked and released a redacted version of it with many sections blacked out in January 2023. 

As part of the licence application, the NNR started a public consultation process on 8 January 2023 with a deadline for submissions on 16 March 2023. Due to the lack of transparency from Eskom, civil society organisations have rejected this process and demanded the complete suspension of the comment period.

Continue reading

IAEA report reveals 14 safety issues with Koeberg

In March 2022 a team from the International Atomic Energy Agency (IAEA) visited Koeberg to report on how ready the plant was to implement Eskom’s plan to extend its life beyond 2024. Eskom wanted to keep this report secret, but due to a request under the Promotion of Access to Information Act, it is now public.

The report lists fourteen safety issues with the planned life extension, or LTO (Long Term Operation), which mostly highlight that given the current conditions at Koeberg, the refurbishment cannot be done on time, nor safely. The full report is included below.

Continue reading

Koeberg costs South Africa

The Koeberg nuclear plant is the only nuclear power plant in Africa. Construction began in the 1970s and the plant came online in 1984. It operates under a licence from the National Nuclear Regulator (NNR) which expires in July 2024. In 2010 the Eskom Board approved spending R20bn on refurbishing Koeberg to extend its life by 20 years, provided that it received approval from the NNR. That approval has not as yet been given to Eskom by the NNR.

Currently Koeberg provides 3.5% of national nominal generating capacity, although over the past few years it has been plagued by problems. For most of 2022, unit 2 has been offline and the plant has run at half of its nominal capacity.

Continue reading

Modelling report: Koeberg life extension costs the country

It is generally agreed that nuclear power comes with an inherent risk. What is hotly debated is whether or not there are benefits which outweigh that risk. When it comes to the Koeberg Nuclear Power Plant, Eskom have had the approach that since Koeberg produces electricity at a cost of around R0.45 per kWh, it is a ‘no-brainer’ to spend whatever is needed on a refurbishment to extend the life of the plant beyond the end of its design life in 2024.

A recently released modelling report estimates that doing that refurbishment would result in additional costs of R50bn “from a combination of the actual costs of life extension, additional open cycle gas turbine (OCGT) usage, large key-customer curtailment requests/instructions, and scheduled load-shedding.” It will also increase carbon emissions due to the additional use of OCGTs.

Continue reading

Eskom statement re Koeberg outage confusing and disingenuous

On 15 January Eskom released a statement saying that Koeberg unit 2 “will on Monday 17 January 2022 be taken offline for a regular refuelling and maintenance outage that is scheduled for five months.”

Setting the disingenuous tone
Firstly it is disingenuous to call this a “regular refuelling” outage. It is about as accurate as saying your car is going to the mechanic for refuelling, and by the way while busy filling the tank they will also replace the gearbox. The vast majority of the cost and the duration of the outage will be to do the refurbishment, so it is more accurate to call this a refurbishment outage.

Continue reading

Koeberg airborne contamination incident

Shortly after midnight on 28 October 2021 some test results became available which found excessive levels of Iodine-131 in the ventilation system at the Koeberg nuclear power station. This was likely a result of a test which had been done in the afternoon, combined with faulty filtration systems that meant the Koeberg Security Central Alarm Station (CAS) had to be evacuated.

While it is reassuring that Eskom were testing this safety system, no standard test procedure includes evacuating all staff from the security nerve centre of a nuclear plant. Clearly there was something significantly wrong.

While Eskom has not released much by way of detail, it is likely to be a result of a combination of three factors.

Continue reading

Ministerial agreement contradicts IRP 2019

Too much power

The responsibility of regulating the safety of nuclear installations in South Africa is concentrated in the hands of one man, who appoints not only the members of the National Energy Regulator of South Africa (NERSA), but also the CEO of the National Nuclear Regulator (NNR) , and its board via an opaque process. The same man has committed in writing to both procuring a new nuclear plant by 2024, and extending the life of Koeberg by 20 years beyond its design lifetime.

Ministerial performance agreements address poor service delivery
In 2019, in an attempt to address poor service delivery, President Ramaphosa required each national minister to sign a performance agreement. This was laudable, but in some cases has had unforeseen and negative consequences.

Continue reading

Eskom responds to Koeberg cracks

In response to our press release Cracks in Koeberg Safety Claims Eskom released a statement (full text given below) on 12 February 2021. This statement ignores several of the issues we raised, obfuscates others, and provides some further alarming information.

Maintenance and testing is being done …
The Eskom statement says “repairs have been implemented” which sounds initially reassuring. However, the report itself describes the repairs in progress at the time as follows:Extract from report: neither ideal nor sustainable

Continue reading

Cracks in Koeberg safety claims

A recently released Eskom document revealed that 40 years of exposure to sea air at Koeberg Nuclear Power Station has damaged the concrete of the containment buildings. At one stage the concrete containment dome was found to have cracked around the entire 110 meter circumference.

“The containment buildings are the outer shells of the reactor buildings, built as pressure vessels to withstand the pressure if the reactors inside them ever malfunction and therefore prevent harmful radiation being leaked into the environment,” says DR, a member of Koeberg Alert Alliance (KAA) and a retired analytical chemist.

Continue reading